• 093. ARE Technical: Top 5 Tips for Project Development & Documentation (PDD)
    2026/04/08
    In this episode, David and Eric focus on the ARE PDD (Project Development & Documentation) exam, framing it as the construction documents phase in contrast to PPD’s schematic design and PA’s programming. They emphasize that PDD is less about memorizing content and more about using judgment, coordination, and decision-making at a detailed scale, and while it’s often seen as the most technically demanding division, they argue it’s best understood as an exam about “details and decision making.” Listen to the Audio Show Notes Key Concept: Scale & Phase Differences PA: Programming phase – big-picture, site plan / 1⁄16″ scale.PPD: Project planning & design – floor plan scale (1⁄8″, 1⁄4″), schematic design.PDD: Project development & documentation – detail scale (1⁄2″, 1″, 3″), full detail level.Same topics (structure, ADA, waterproofing, cost, etc.) appear across PA/PPD/PDD, but: The phase and scale determine the right decision, not the topic itself. Tip 1: PDD Is a Coordination Exam Before a Detailing Exam Architects act as coordinators (“master conductors”) among disciplines: Making sure sprinklers, beams, and ducts don’t clash, and that it all looks good. On PDD, the emphasis is: Integration of building materials & systems (~1/3 of exam).Construction documentation (~1/3 of exam). These domains show that PDD is fundamentally about coordination, not just isolated details.Context is critical: Example: vapor barrier placement can’t be memorized as “always on the warm side” – climate, building type, and other conditions change the correct answer.The test is a judgment test, not a pure memorization or math test. Tip 2: Know What Level of Detail Is Appropriate Distinguish what is under the architect’s responsible control vs. contractor’s: Architects do not dictate means and methods.Architects review shop drawings only for design/esthetic intent, not for buildability.Shop drawings and submittals: Shop drawings = detailed drawings (e.g., custom cabinets) by subs.Submittals = cut sheets, product data, samples, mockups, etc., provided by contractor.Architect reviews/approves for design intent, but doesn’t create them. Avoid over‑detailing or chasing hyper‑specific local practices: The exam assumes a general North American standard of care, not one office’s or one region’s quirks. Use rules of thumb, but always understand the why: Foundations below frost line → top of footing must be at or below frost depth (to avoid freeze–thaw heave).Expansive clay → generally go deeper or adjust foundation type.Understanding the reason behind rules allows you to adapt in different scenarios. Tip 3: Systems Questions Are About Selection & Sizing, Not Heavy Calculations Modern ARE format: No calculus or full engineering design.Possible light calculations: CFM, board feet, simple area comparisons, etc. Focus on: Selecting appropriate systems for building type and use. Example: Big-volume church used weekly → CAV system is reasonable.Elementary school with many small zones → CAV would be inefficient. Relative sizing, not exact engineering numbers. Example: Duct sizing based on approximate areas: If 12″×12″ (144 in²) doesn’t fit, 10″×15″ (150 in²) is “good enough.” Use common sense and elimination, not perfectionism. Strategy: Know a handful of basic formulas as backup.Understand how to apply them and what the quantities represent.Adopt a “reasonable and works in practice” mindset rather than “exact to three decimals.” Tip 4: Construction Documents Communicate, They Don’t Explain CDs are meant to: Be bid, permitted, and built from.Communicate design intent, not act as step‑by‑step instructions. Good CDs: Use coordinated plans, sections, details, schedules, and keys to convey information clearly and consistently.Avoid long explanatory paragraphs; if a detail needs a paragraph to explain it, it’s probably a bad or overly complex detail. Varying levels of completeness: Permit sets: Only enough for code review and approval; minimal extras.Bid sets: More detail on scope and quantities so contractors can price.Construction sets: May go further for clarity, but still aren’t “assembly manuals.” CD standard: Clarity over cleverness; communicate efficiently and consistently. Tip 5: Codes and Costs Are Filters at the Detail Level Architects are not cost estimators: Costs fluctuate daily; the exam expects conceptual understanding, not dollar-accurate pricing.Example: Galvanized < Stainless < Copper in relative cost; exact numbers not needed. Code and ADA at the detail level: Aim for detailed‑level compliance (meeting intent within real‑world tolerances).Buildings are not built to 1/32″; materials move, contractors shim and adjust. In AIA B101: Architect provides an “estimate of the Cost of the Work” at the end of each phase (SD, DD, etc.), often by: SF ...
    続きを読む 一部表示
    42 分
  • 092. ARE Technical: Top 5 Tips for Project Planning & Design
    2026/03/27
    David and Eric discuss how PPD fits into the ARE sequence, how it differs from other divisions (especially PDD), and five key mindset/strategy tips for candidates. The main emphasis: PPD is about integration and judgment, not memorizing formulas or hyper‑detailed systems data. Listen to the Audio Show Notes Candidates often see PPD as “the big one” and psych themselves out.Compared to exams like PcM, PjM, CE, PA, PPD and PDD: Are longer and more technically demanding.Test how “architect‑like” a candidate thinks. Other divisions feel more siloed (e.g., contracts, firm types, corporate structures).PPD throws in multiple dimensions at once: cost, aesthetics, structure, codes, ADA, systems, site, climate, etc. → The challenge is the breadth and integration, not obscure content. Tip 1 – PPD is an Integration Exam, Not a Systems Exam PPD’s biggest module is Project Integration, and that’s where many struggle.The architect is the “conductor”: Coordinates structural, mechanical, electrical, code, and owner requirements.No one else on the team is integrating all of this. On questions: Don’t fixate on missing info (“that depends…”).Focus on the one or two key clues NCARB gives you.You’re not picking the perfect answer, you’re picking the best answer among several “good” ones.This requires adopting a realistic architect mindset (compromise, “good enough,” best fit). Tip 2 – Let Site and Climate Drive Design Decisions PPD is basically the schematic design phase: Programming is done; spaces and relationships are known.Now you must actually place and shape the building on its site. Candidates often underuse: Sun path, wind, micro vs. macro climate, orientation. Example: If the question says “Phoenix, Arizona,” that’s a huge clue: hot, dry climate → certain orientations and shading strategies are clearly better. Many candidates: Treat climate as secondary.Have never used a sun chart or don’t know they vary by latitude. Key message: If your design ignores the site and climate, it’s likely wrong – and NCARB is explicitly testing that. Tip 3 – Codes Shape Design; They Don’t Kill It Code thinking evolves across phases: Programming/PA: basic occupancy type, rough allowable height/area (e.g., table 503).PPD / schematic design: feasibility and layout: Allowable building height & area.Occupancy separations.Egress requirements and egress strategy. Codes aren’t “copy‑paste” details: Architects interpret the code and its intent.Egress, ADA, etc., are designed experiences, not just diagrams. Relationship to PDD: In PPD you decide: building type, heights, separations, general strategy.In PDD you detail and carry out those decisions. Bonus point: When codes conflict, it’s not either/or: You must comply with both; practically, you follow the more restrictive so both are satisfied. Tip 4 – Systems Questions Are Conceptual, Not Calculational PPD = still schematic design → things are fluid, nothing is sized to the last CFM.You might see very light “back‑of‑the‑envelope” math, but: Focus is on choosing appropriate systems conceptually, not crunching numbers. Example: Church used mainly on Sundays → large volume, infrequent use → CAV system makes sense.Music studio with small rooms: CAV could be noisy and inappropriate.Hydronic or quieter solutions may be more suitable. You use: Use type, occupancy pattern, acoustics, flexibility, climate as clues. Again: there is no “perfect” system, only the most appropriate given the clues.Don’t silo PPD vs. PDD: PPD‑style conceptual questions can show up on PDD, and vice versa.NCARB expects flexible knowledge application. Tip 5 – Budget Is a Design Constraint, Not a Math Problem In schematic design you do not: Produce detailed cost estimates or exact per‑unit pricing. You do: Understand relative costs: Brick vs. CMU: similar order of magnitude but different roles.Core‑ten vs. ACM panel vs. stucco.Marble countertop vs. plastic laminate. Recognize major cost drivers: Deep underground parking.High water tables and hydrostatic pressure.High‑performance envelopes for hurricane/tornado zones. As per B101 (Bonus Tip): Architect provides an estimate of the Cost of the Work at each phase (SD, DD, CD).Detailed cost estimates are typically done by a third‑party cost estimator or contractor, or as an additional service. Exam wise: If the owner wants a detailed cost estimate at SD, that’s unrealistic.PPD focuses on: “Given this budget constraint, which design move is more appropriate?” Closing Points from the Episode PPD vs. PDD distinction: PPD: concept, integration, “we’ll figure that out later.”PDD: “there is no later” – now you must detail and make it buildable. Candidates must: Stop chasing perfect answers and precision they don’t have at schematic phase.Work with clues, appropriateness, standard of care, and ...
    続きを読む 一部表示
    34 分
  • 091. ARE Technical: Top 5 Tips for Programming & Analysis (PA)
    2026/03/20

    David and Eric discuss five tips for passing the programming and analysis (PA) division of the Architect Registration Examination (ARE). They emphasize that PA is about evaluation, not design, and highlight the importance of using highlighting tools for long, wordy questions. They stress that programming focuses on constraints before opportunities, using codes and zoning as filters, and that economics matter at a high level. Programming is about relationships and feasibility, not just square footage. They also note that PA questions are longer, providing more clues for candidates to use.

    Listen to the Audio

    Show Notes

    A. Setup & Mindset Shift

    • Why PA feels so different from PCM / PJM / CE and PPD / PDD
    • PA = gray area, long wordy questions, more about judgment than memorization
    • Bonus: practice using the exam highlighter—critical for PA’s long questions

    B. What PA Is Really About

    • Programming phase = problem seeking, not problem solving
    • No design yet: you’re evaluating constraints, feasibility, and relationships
    • You’re analyzing inputs: site, climate, soils, codes, zoning, owner’s program

    C. Five Core Tips

    1. Stop Designing – Evaluate, Don’t Solve
      • You haven’t designed anything yet
      • Compare options, surface risks, and recommend feasibility
      • Bubble diagrams and big‑picture fit, not plans and details
    2. Start With Constraints Before Opportunities
      • Environment + context: sun, wind, soils, climate, topography, neighbors
      • Look for what cannot be done first, then what could be done
      • Treat this as due diligence at the very start of a project
    3. Codes & Zoning Are Filters, Not Afterthoughts
      • Use setbacks, easements, FAR, occupancy, construction type as early filters
      • Goal: define the buildable area / envelope and check viability
      • You’re not doing deep PPD/PDD code work—just feasibility‑level analysis
    4. Programming = Relationships More Than Square Footage
      • Quantitative: room sizes, totals
      • Qualitative: adjacencies, privacy, sound, light, experience
      • Residential example: public vs. private zones, don’t dump a powder room on the kitchen
      • Good programs describe how spaces relate and feel, not just how big they are
    5. Economics Matter, But Only at a High Level
      • Rough cost per SF or per unit to test viability, not detailed estimates
      • Don’t blindly pick the cheapest option; PA is not a bid
      • Think: “Is this project basically viable on this site with this program?”

    D. How PA Connects to PPD & PDD

    • PA, PPD, PDD as three views of the same project at different scales
    • Studying PPD can make a PA retake easier (you see the “other side” of programming)

    E. Big Takeaway

    • You pass PA by thinking like an architect at the very beginning of a project:
      curious, constraint‑driven, feasibility‑focused, and comfortable in the gray area.

    Please Subscribe

    Receive automatic updates when you subscribe below!

    Please rate us on iTunes!

    If you enjoyed the show, please rate it on iTunes and write a review. It would really help us spread the word about the ARE Podcast. Thanks!

    続きを読む 一部表示
    42 分
  • 090. ARE Mentor: The Identity Shift
    2026/03/16
    This episode, “The Identity Shift,” is for ARE candidates who are close to finishing but feel stuck or suddenly full of doubt. David reframes that experience as a normal transition from student to licensed architect, where imposter syndrome, fear of passing, and completion anxiety are signals of change—not failure. Listen to the Audio Show Notes I. Why the Final Phase Feels Different Heaviness of the last exams Often PPD/PDD: more technical and denseEmotional weight added because the end is near Perception of “struggling” Thoughts like “I don’t know anything,” “I’m not ready,” “Why is this harder now?”Core idea: you’re not struggling, you’re transitioning II. Common Emotional Patterns & “Misreadings” Imposter Syndrome Fear of being “found out” or exposed“People think I know all the answers because I’m about to be licensed”Normal and common across professions Fear of Passing (not just fear of failing) Anxiety about: “What comes next if I actually achieve this?”Unfamiliar emotion for many candidates Completion Anxiety What happens after finishing a long-term goal?Self-doubt, fear, and discomfort misread as “red flags”Reframed as signals of change and signs of transition III. The Core Concept: The Identity Shift From learner to decision-maker You’ve been in a learning phase (“sponge mode”) for 1+ yearsTransition to phase where you must: Make judgment callsTake ownership of decisions Change in professional identity From “ARE candidate/student” to licensed architectExpectations from others increase (even if already making decisions at work)Your input begins to carry more weight and influence Loss of the “student” comfort zone Student role feels safe: “Pressure isn’t fully on me yet”After licensure: harder to hide behind “I’m just a student”Brain reacts with self‑protection: “I’m not ready, I don’t know enough” IV. How the Brain Protects the Old Identity Delaying tactics Postponing exams (“I’ll take it in summer/fall when I’m more ready”)Easing off studying due to fear and doubt Attachment of big life decisions to licensure “Once I get licensed, I’ll…” Leave my firm / change jobsMove to a new city (e.g., NYC, Seattle)Get married / have a baby As licensure gets close, all those attached decisions feel suddenly “due” V. Readiness and What the License Really Means The myth of feeling “ready” Nobody truly feels ready to protect health, safety, and welfareARE tests minimum competency, not total mastery License as confirmation, not creation, of capability You’re already: Solving problemsExercising judgmentContributing to real projects License makes the ownership of that judgment more visible License as a “license to learn” Parallel to getting a pilot’s licenseLearning doesn’t end at licensure; it actually begins a new phaseArchitecture as a path of lifelong learning and growing responsibility VI. Practical Recommendations Don’t change your overall approach Keep your existing study system and strategy Focus on execution and routine Study habitsPractice examsTime managementKeep it simple and consistent Suggested study cadence Study 6 days/week, with Friday offEven 20 minutes/day counts—maintain daily “touches” to keep momentum VII. Final Mindset and Encouragement Embrace the transition Acknowledge fear, imposter feelings, and anxiety as normalSee them as signs you’re close to the finish line Double down on commitment Resist self-sabotage: Imposter talkSelf-doubtPostponing exams without real cause The reward on the other side Strong sense of pride, self-satisfaction, and accomplishmentYou “walk a little taller” at work as a licensed architect Core reassurance If you’ve come this far, you’ve earned the right to call yourself a licensed architect— you just need to cross the finish line. Please Subscribe Receive automatic updates when you subscribe below! Please rate us on iTunes! If you enjoyed the show, please rate it on iTunes and write a review. It would really help us spread the word about the ARE Podcast. Thanks!
    続きを読む 一部表示
    20 分
  • 089. ARE Technical: Top 5 Tips for Construction & Evaluation (CE)
    2026/03/13
    This episode of the ARE podcast gives five key tips for passing the ARE Construction & Evaluation (CE) exam. The focus is on thinking like an architect under the AIA contracts, emphasizing standard of care, observation vs. construction, administrative procedures, question-reading strategy, and performance-focused closeout/post-occupancy work. Throughout, they stress judgment, restraint, documentation, and staying within professional/contractual boundaries. Listen to the Audio Show Notes Main Tips (1–5) 1. Answer from the Architect’s Contractual Role (Standard of Care) Always answer exam questions from the standpoint of the architect’s contractual role, not your personal or local practice.Think in terms of standard of care: What would any reasonably prudent architect do in this situation, based on the information given? Deep or specialized experience can hurt you on the exam if you override the “standard” approach with niche real-world habits.CE is a national, standardized test, not region-specific.Focus on: Roles, responsibilities, and authority during construction.Who has/produces/reviews which documents.Who can stop the work, what “observe” means vs. “inspect,” etc. 2. Construction Observation (Architect as Observer, Not Builder) In CE/Contract Administration, the contractor’s job: Build in conformance with the contract documents.The architect’s job: Observe whether work conforms to the contract documents and report findings to the owner.Key boundaries: Do not dictate means and methods—that’s the contractor’s domain.Shop drawings: Produced by the contractor, not by the architect.Architect reviews them only for design/esthetic intent, not for how to build.They are not part of the contract documents. Nonconforming work: The owner has the right to accept nonconforming work (A201).Architect must inform the owner of implications so they can make an informed decision. Field reports and site visits: Document date, time, weather, observed conditions.Not a guarantee or full inspection of all work.Architect only visits as frequently as the contract requires, often at agreed milestones (e.g., foundation completion, framing completion). 3. Administrative Procedures (The “AIA Way”) CE is less about technical minutiae (e.g., OSB vs. plywood) and more about admin processes and AIA contracts.Critical procedures and documents: Submittals & shop drawingsRFIsApplications for paymentLien release formsChange Orders (COs)Construction Change Directives (CCDs)Project ManualSubstantial Completion & Project Closeout Core contracts: A201 – General Conditions (owner/architect/contractor relationships and responsibilities).B101 – Owner–Architect AgreementA101 – Owner–Contractor Agreement Why the architect reviews applications for payment: Owner is not expected to understand construction.Since architect observes the work, they can verify claims like “50% framing complete.”Also logical for architect to review lien waivers in relation to paid work. “There’s the right way, the wrong way, and the AIA way”: For the exam, the AIA way is what matters, and it usually aligns with industry practice.Deviating from it in practice can increase liability. 4. Reading Questions for Timing & Keywords (First / Best / Most Appropriate) Many wrong answers come from misreading or reacting too quickly, not from ignorance.Pay close attention to timing/context words: “First” thing you should do“Best” action“Most appropriate” response Always ask: What phase are we in? (Construction admin? Multi-phase project? Pre-bid?)What logically happens next in the process? Exam traps: Fake urgency: e.g., owner is on vacation and unreachable, contractor “needs” a decision. Your roles and responsibilities do not change. If the owner hasn’t appointed a representative, you wait. Multiple answers may be true statements, but: You must pick the one that actually addresses the question asked and fits the given context and timing. In their coaching sessions, candidates rarely reach consensus on answers at first, showing how easily people: Justify multiple answers as “true,” butMiss what the question really asked. 5. Post-Occupancy Evaluation & Closeout – Focus on Performance, Not Blame Post-Occupancy Evaluation (POE), substantial completion walk-throughs, punch lists, and final closeout are about performance: Does the building perform as intended?Are systems functioning properly?Are design goals (e.g., better test scores via daylight and ventilation) being met? It is not about blame or combative architect vs. contractor dynamics.POE is not part of the basic services in B101: Basic services end when the architect signs the final application and certificate for payment (changed from “60 days after substantial completion” in 2007). Contracts (B101 and A101) are the framework: They define what each party has promised to ...
    続きを読む 一部表示
    30 分
  • 088. ARE Mentor: Course Correcting After Failure
    2026/03/10
    David discusses how to course correct after failing an ARE exam. He explains why one failed division shouldn’t create a negative narrative and reminds candidates that failure simply means retaking the exam. He also covers how to review the score report, keep momentum by scheduling the next exam about eight weeks out, and use practice exams to better understand the format. The focus is simple: adjust your strategy and keep moving forward. Listen to the Audio Show Notes Introduction & Purpose Addressing listeners who recently failed an ARE examBrief on ARE Mentor vs. ARE Technical episodesMain goal: protect momentum and prevent derailing after a failure Mindset: Don’t Turn One Failure Into a Story How we create negative narratives after failing (imposter syndrome, “I’m bad at tests,” etc.)Core reframe: a failed exam only means you have to take it againWarning against letting a single result become your identity or long-term story Using the Score Report (But Not Overusing It) Look at the score report briefly to see: Where you were weakestWhere you were strongest Reference to Episode 85 – ARE Technical: Analyzing the Score ReportEmphasis that the score report: Doesn’t mean as much as people thinkShould be reviewed for a few minutes, then filed away Encouragement to rely on honest self-assessment of weak areas Staying in the Exam Cycle & Avoiding the “Same Division Loop” Personal story: failing Programming & Analysis (3.0) and waiting two years for the next examAdvice: Don’t take months offDon’t pause studyingDon’t delay scheduling the next exam The “same division loop”: Example: fail PCM, wait 60 days, insist on retaking PCM before moving onResult: loss of momentum Strategy: Schedule the next division immediately after a failAim for about 7–8 weeks out Momentum Analogy: Flat Tire on a Road Trip Failure = flat tire, not the end of the journeyYou don’t turn around and go home; you: Change the tireContinue the cross-country trip Same idea with the exam process: fix, adjust, move forward Strategic Use of the 60-Day Retake Window General pattern: Schedule a new division ~8 weeks outTake that new-division examFit the retake shortly after: PCM, PJM, CE, PA: about 1 weekPPD, PDD: about 2 weeks After the retake, jump into the next division Rationale: protect and extend momentum, avoid long study gaps Self-Analysis: Identifying What Actually Happened Go beyond the score report into self-awareness: Where did the exam start feeling hard? Case studies?Technical questions?Time pressure?Unfamiliar topics? Use these questions to pinpoint weak areas Common Patterns & What They Mean Questions felt unfamiliar (even though you studied) Often means you studied too narrowlyUsually clustered in specific modules, not the whole exam Running out of time / feeling rushed Time management is a major hurdle, especially after long gapsYou don’t fix time management in theory; it requires real exam reps Backpacking analogy: You become a better backpacker by going backpackingDay hikes and training help, but can’t replace multi-night tripsSame for exams: practice actual NCARB exams to build timing skills Making the Most of NCARB Practice Exams NCARB practice exams as: A window into how NCARB thinks about questionsEspecially crucial in the final week before the exam How to use them: Don’t treat them just as a percentage scoreReverse engineer: Handwrite notes and diagramsMark why wrong answers are wrongCircle keywords and patterns Treat them as a guide to NCARB’s logic, not a mere score predictor Emotional Recovery & Course Correction Normal emotional reaction to failing: Imposter feelings“I’m never going to finish”“I’m not ready” Advice: Allow yourself to feel those emotionsThen course correct rather than stay stuck Reframing the episode: It’s about course correcting after a failureFocus on protecting your momentum Core Process & Closing Message Core rhythm promoted in the coaching program: Study → Test → Analyze → Repeat Protecting momentum: Stay in a rhythm rather than stop-start cycles Closing encouragement: Think consciously about how to protect your momentum this weekKeep moving through the cycle until you get your license Please Subscribe Receive automatic updates when you subscribe below! Please rate us on iTunes! If you enjoyed the show, please rate it on iTunes and write a review. It would really help us spread the word about the ARE Podcast. Thanks!
    続きを読む 一部表示
    16 分
  • 087. ARE Technical: Top 5 Tips for Project Management (PjM)
    2026/03/06
    In Episode 87 of the ARE Podcast, David and Eric break down the five most important strategies for passing the Project Management (PjM) division and how to think like a project manager on exam day. We begin with discussing the top five tips for project management, focusing on the AIA Contracts B 101 and A 201, which outline the roles and responsibilities of the owner, architect, and contractor. We emphasize the importance of understanding these documents for both the ARE exam and real-world practice. We also cover accounting in project management, which involves tracking changes and staff utilization, and the nuances of project delivery methods. Additionally, we discuss the differences between owner’s consultants and architect’s consultants, the significance of bonds and insurance, quality assurance and control processes, and the distinction between billable and direct labor rates. Listen to the Audio Show Notes Understanding the AIA Contracts David introduces the episode, focusing on the top five tips for project management, specifically the AIA Contracts B101 and A201.Eric emphasizes the importance of familiarizing oneself with these documents, noting that they are readily available online and through NCARB.David explains the B101 (Owner–Architect Agreement) and its significance in understanding architect services and roles during contract administration.They discuss A201 (General Conditions of the Contract for Construction) as covering applications for payment, schedule of values, and the different ways to handle changes (change orders, CCDs, ASIs). Accounting in Project Management They discuss accounting in project management as different from accounting in practice management.Focus is on: Tracking changes to contracts.Tracking schedules and fees.Staff allocation and hours. David notes it is more staff / personnel related: allocating hours, making sure the team doesn’t exceed budgeted hours.Eric stresses thinking like a project manager, not an employee: Don’t always pick the most “qualified” staff person if their utilization is already very high.Look for underutilized staff and opportunities for mentoring and growth. Project Delivery Methods They review the main project delivery methods: Design–Bid–Build (DBB)Design–Build (DB)Progressive Design–BuildConstruction Manager at Risk (CMAR)CM as Contractor and CM as AgentFast-track as a modifier to multiple methods Eric explains: exam questions are usually asking for the most appropriate method given a specific context, not just “a method that could work.”David notes that for public work, NCARB tends to see Design–Bid–Build as the default because: It is traditional.It supports fairness and transparency. Eric expands on CM at Risk: Contractor is on board early.Provides continuous pricing and helps maintain a GMP.Good for complex projects and for controlling cost and risk. They briefly mention Integrated Project Delivery (IPD) as an advanced form often used for highly complex buildings (e.g., labs). Owner vs. Architect Consultants Architects’ typical consultants: Mechanical, electrical, plumbing engineers.Structural engineer.Landscape architect. These are architect’s consultants: Their fees are included in the architect’s proposal.Architect manages and coordinates them. Owner’s consultants (e.g., AV consultant, security consultant, drapery consultant): Hired and paid directly by the owner.Architect still must coordinate their work with the project, but does not manage them. David gives the example of a drapery consultant: Architect provides floor plans, door/window schedules, head and jamb details.Architect is not calling to check orders, delivery, and installation—that is the owner’s role. Under B101, MEP and structural are part of the architect’s basic services, even though the actual work is done via consultants. Bonds and Insurance Eric frames bonds as a form of insurance for the owner.Key bond types to know: Bid Bond – assures the contractor will honor its bid.Performance Bond – assures the contractor will complete the work per contract.Payment Bond – assures subs, suppliers, and labor are paid. Many other bond types exist, but exam focus is on the major ones.David notes that under B101, the architect typically carries five types of insurance: Workers’ compensationAutomobile insuranceProfessional liability insuranceGeneral liability insuranceEmployers’ liability insurance (added in 2017) Distinction between: What states require (e.g., only workers comp and auto in some states).What B101 contractually requires if not amended. Quality Assurance (QA) and Quality Control (QC) QA/QC processes in offices: Checklists, internal reviews, “red team” reviews.Standard procedures to ensure a consistent standard of care. For complex projects (e.g., with specialized or “wacky” equipment): Extra coordination, double- and triple-checking.Use of equipment/...
    続きを読む 一部表示
    31 分
  • 086. ARE Mentor: Schedule the Exam Before You Feel Ready
    2026/03/03
    In this episode, David emphasizes the importance of scheduling the your first or next Architect Registration Examination (ARE) before feeling fully ready. He shares his personal experience, noting it took seven years to complete due to procrastination. He then highlights the psychological barriers, such as fear of failure and the desire to feel confident, that delay scheduling. Finally he advises setting specific dates and maintaining consistent momentum. David also suggesst taking eight to ten exams a year to complete the six divisions within 12 to 24 months. The key is to schedule exams to create urgency and focus, transforming study into structured training. Listen to the Audio Show Notes Scheduling the Exam Before Feeling Ready David emphasizes that waiting to feel completely confident before scheduling an exam is unrealistic and leads to prolonged preparation.He shares that it took him seven years to finish the exams largely because he kept delaying scheduling.Common excuses include: “I’ll schedule once I’m scoring higher on the exam simulator.”“I’ll schedule once I get through more content.”“I’ll schedule when work slows down.”“I’ll schedule when I feel more confident.” David argues that readiness is not a feeling; it’s a decision. Without a test date, there’s no pressure, no urgency, and no forcing function. Challenges of Scheduling an Exam David tells a story from 2013–2014 when he started an online study group for the CSE: Out of about 14 people, only one scheduled their exam in the first week. This revealed deeper reasons why candidates avoid scheduling.Scheduling makes the process real: Now there’s a clock.Now there’s a risk.Now there’s the possibility of failing. As a result, people stay in “preparation mode”: It feels productive but is ultimately safe.David notes that “safe studying” doesn’t pass exams—deadlines do. He explains the “deadline effect”: A real date changes how we prioritize.We shift from over-highlighting and passive study to practice and performance. David stresses the importance of being specific: “I’ll take it in April” is vague.“I’m taking it on April 25” is specific and creates focus and accountability. Fear of Failure and the Importance of Deadlines A major reason candidates avoid scheduling is: “What if I fail?”David points out that if you never schedule, you never have to confront failure—but you also never move forward.He frames failure as: A normal part of life and growth.Central to every success story. David notes that we often learn more from failures than successes.He clarifies that there’s no real-life risk in failing an ARE exam: The true risk is dragging the process out for years and constantly resetting momentum. He shares his experience with general structures: Studied for it three separate times over two years.Each time he got close, didn’t take the exam, then had to restart later.Ultimately passed because he knew the material so well—but paid a heavy price in energy and time. Impact of Life and Consistency on Exam Preparation David acknowledges that life gets in the way—work, projects, and responsibilities.In his coaching program, many candidates: Are in and out of the process for years.Have taken prior versions of the exam (3.0, 4.0) and lost credits. He emphasizes: The importance of consistency.Not letting life continually derail progress. David notes that NCARB removed the five-year rolling clock, which: Removes external urgency.Makes it easier to stretch the process out unnecessarily. Beginning with the End in Mind David recommends scheduling the exam first, before deep-diving into content: “Begin with the end in mind.” This approach: Creates urgency, focus, and discipline.Prevents endless, drifting study. He advises: If you start studying today, schedule the exam today.Aim for 6–8 weeks out, not more. David encourages taking exams consistently: Pass or fail, keep moving to the next division.Don’t wait to pass one division before starting to study the next. Building Momentum: Exam Strategy and Timeline In his program, David encourages candidates to plan for 8–10 exam attempts per year: That covers all six divisions plus retakes. Typical path: Take an exam roughly every two months.Fit retakes in between if needed. With this momentum: Many candidates can be licensed in 12 months.For others, 18–24 months should be enough if they’re consistent. Psychological Shift and Empowerment When you schedule, you shift from studying to training: You now have intention, structure, and stakes.Training ends on test day, then you move on to the next division. David emphasizes that scheduling is an act of empowerment: You decide: “I’m in control of this process.”You commit to your license and refuse to be “wishy-washy” about your goals. He encourages adopting a determined mindset: You want your license.You ...
    続きを読む 一部表示
    19 分